Gallery of images 5 - building the nuclear power station
View of space for 1st (north) Pressure Vessel
Steelwork and concrete
Re-lifting operations for steel plate girder
View onto formwork for bottom of 1st Pressure Vessel, showing steel prestressing anchors around one boiler position
View of site from northwest
View down onto base of 2nd Pressure Vessel
Detail of precast units showing the wire winding channels, and the support system for the precast units, and to the right, prestressing anchors
Steel beams for lower EOT in place, steel plate girder for upper EOT ready for lifting
Detailed view of No.54 with Reactor Hall concrete frame structure surrounding the Pressure Vessel
View onto Pressure Vessel formwork showing some precast units in place, some prestressing anchors around one boiler location and elsewhere, and formwork still under construction for beneath the reactor. |
|
||||